    I asked Nigel about the delay and here is his reply:


    "Good morning Roger


    I pass this site frequently and noticed apparent little change - or no change, so asked for a report on the progress.

    Buckland Bridge to Lorne Road - section complete.

    Buckland Avenuie to Barton Road/Cherry Tree Avenue Junction - awaiting disconnection of electrical connection to existing signs - signs will then be relocated at the back of the footway and reconnected with the final surfacing laid to complete - should be done in the next two weeks.

    Barton Path - works complete including improved lighting other than a couple of minor issues with the most noteworthy being a tree stump that is raising the river wall coping - expected that these will be dealt with in about a weeks time if not already done.

    Frith Road Junction and Maison Dieu Road - programmed to commence on 13th June which means that all should be clear in time for Dover Carnival on 3rd July.

    The scheme has not run out of money and is proceeding - other sections will follow on.

    Regards




    Nigel"


    So it's not run out of steam (or money) but waiting on others.



    Roger