    Piling rigs on site currently working on block C , they will then move to block D & join other piling rigs to complete block A . New electricity sub station to be connected to rear of Dolphin House then existing to be demolished. BT are moving in to divert fibre optics from old P&O /former AA site. Infilling excavation works is moving ahead with other utility services being completed. Hotel & cinema sites being prepared for steel frame works to start. Piling completed on these sites. That was up to yesterday.