    St. James Development progress
    Travelodge Site - work starts installing first floor pre-cast concrete window sections, following scaffolding work from local contractor




    Elsewhere on site - scaffolding and netting installed last week on Block A (alongside Townwall Street) and roofers started work today




    further steels have arrived for Block C over by Dolphin Passage, and concrete flooring continues to be laid in Block A.

    More 'town wall' sections were installed last week at the M&S end of Block A.


    A shot of the St. James site taken in the afternoon of 3rd May from Western Heights