Having completed the Pier A extension and the refurbishment of berth ED3, the next big job is the refurbishment of berth ED6.
Part of the old hoverport is going to be used for fabrication and a floating crane will be shuttling back and forth between ED6 and the Prince of Wales pier.
DOVER HARBOUR BOARD
MARINE SERVICES DEPARTMENT
Notice to Mariners 35/2012
BERTH 6 FLOATING CRANE HEAVY LIFT 17 - 21 DECEMBER 2012
As part of major berth replacement works, notice is hereby given that a floating crane will be conducting heavy lifts in the vicinity of Berth 6 and transiting large sections of steel across the harbour to the Prince of Wales Pier during the period 17 - 21 December 2012
Mariners are advised to exercise caution when manoeuvring in the vicinity of Berth 6 whilst lifting and transit is in progress and should contact Dover Port Control if in any doubt.
Paul Brown 13 December 2012
Harbour Master